What Is a Lien Waiver?
A lien waiver is a short signed paper. In it, a contractor, sub or supplier gives up some or all of its right to put a lien on the property, usually in exchange for a payment.
Why lien waivers exist
Anyone who improves a property and is not paid can usually put a mechanics lien on that property. A lien is a claim against the land itself. It can block a sale or a refinance, and in the end it can force a sale to pay the debt. That is strong protection for the people doing the work.
It is also a risk for the owner and the lender. They can pay the general contractor in full and still face a lien from a sub the general contractor never paid. The lien waiver is how they manage that risk. Each time money moves down the chain, the party being paid signs a waiver for that payment. The owner and lender collect them and keep them with the pay application.
The four types
Most waivers fall into four types. They come from two questions.
- Progress or final? A progress waiver covers one payment, through a stated date. A final waiver covers the whole job, usually including retainage.
- Conditional or unconditional? A conditional waiver only takes effect once the payment actually clears. An unconditional waiver takes effect the moment you sign it.
So you get conditional progress, unconditional progress, conditional final and unconditional final. The safe pattern is simple: sign conditional when you bill, and unconditional only after the money is in your account. See conditional vs unconditional for the details.
What a waiver should say
A good waiver names the project and the property, the party signing, the party paying, the amount, and the date the work is covered through. It should also list any exceptions: retainage still held, disputed change orders, or extra work not yet billed. Anything not listed as an exception is usually given up.
Statutory forms
Some states write the waiver wording into the statute. In those states a waiver that does not follow the statute may not count, and a waiver that does follow it is read the way the statute says. States with a required form in our reference: Arizona, California, Florida, Georgia, Massachusetts, Michigan, Mississippi, Nevada, Texas, Utah, Wyoming. Everywhere else, the parties can use their own wording. Check your state's statute before relying on a form.
Common mistakes
- Signing an unconditional waiver before the check clears. If the check bounces, the lien right may be gone.
- Signing a final waiver while retainage or a change order is still unpaid, with no exception written in.
- Waiving through a date later than the work actually billed.
- Losing the signed copies. A waiver you cannot find protects nobody.
- Collecting a waiver from the sub but not from its suppliers. Lower tiers can lien too.
Who asks for them
The owner asks the general contractor. The lender asks the owner and the general contractor, often for every sub who billed that month. The general contractor asks its subs, and the subs ask their suppliers. On a financed job, a missing waiver is one of the most common reasons a draw is held.
Make one
The free lien waiver generator builds all four types from one set of fields and uses the statutory wording where our reference has it.
Frequently asked
What is a lien waiver?
A signed document in which a contractor, sub or supplier gives up some or all of its right to file a mechanics lien, usually in exchange for a payment.
What are the four types of lien waiver?
Conditional progress, unconditional progress, conditional final and unconditional final.
When should I sign an unconditional lien waiver?
Only after the payment has cleared your account. Before that, sign a conditional waiver.
Does every state have a required lien waiver form?
No. Only some states set the wording in their statute. Check your state's page and its statute.