Mississippi Lien Waiver Form & Requirements

What a contractor, sub or supplier in Mississippi needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make a Mississippi lien waiver - free Calculate your Mississippi lien deadlines

Is there a required Mississippi lien waiver form?

Yes. Mississippi sets out the waiver wording in its statute (Miss. Code § 85-7-433). The forms are: Interim Waiver and Release Upon Payment; Waiver and Release Upon Final Payment. A waiver that does not follow the statute may not count.

You must use the statute's forms. A form that leaves out the statutory notice language on its face cannot be enforced. The statutory forms include a notary block (sworn and subscribed). If payment does not arrive, the signer has 60 days after the date in the waiver to file an Affidavit of Nonpayment. Otherwise the signer is treated as paid.

Statute: Miss. Code § 85-7-433

Does a Mississippi lien waiver need to be notarized?

Yes. A notarized signature is required.

Statute: Miss. Code § 85-7-433

Conditional vs unconditional in Mississippi

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

In Mississippi the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.

Mississippi mechanics lien deadlines

StepDeadlineStatute
Preliminary noticeNo general requirement found-
Lien filing - general contractor90 days after last furnishing (the last day you worked or delivered)
Record the claim of lien with the chancery clerk within 90 days after your last work, labor, services or materials.
Miss. Code § 85-7-405(1)(b)
Lien filing - subcontractor90 days after last furnishing (the last day you worked or delivered)
Subs have the same 90-day deadline.
Miss. Code § 85-7-405(1)(b)
Suit to enforce the lien180 days after the lien being recorded
The lien ends 180 days after it is filed if no payment action has been filed by then. If the owner files a notice of contest, the lien ends 90 days after that notice. Whichever comes first applies.
Miss. Code § 85-7-423(3)

Who gives notice: On commercial work, contractors and first-tier subs give no notice before work. A commercial sub-subcontractor must give the GC written notice within 30 days of starting work (§ 85-7-407(2)). Check this point in the statute. A residential sub gives the owner a 10-day Pre-Lien Notice (§ 85-7-409).

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Mississippi

A residential sub must give the owner a 10-day Pre-Lien Notice before filing (§ 85-7-409).

Frequently asked

Is there a required Mississippi lien waiver form?

Yes. Mississippi sets out the waiver wording in its statute (Miss. Code § 85-7-433). The forms are: Interim Waiver and Release Upon Payment; Waiver and Release Upon Final Payment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.

Does a Mississippi lien waiver need to be notarized?

Yes. A notarized signature is required. Statute: Miss. Code § 85-7-433. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Mississippi?

General contractor: 90 days after last furnishing (the last day you worked or delivered) (Miss. Code § 85-7-405(1)(b)). Subcontractor: 90 days after last furnishing (the last day you worked or delivered) (Miss. Code § 85-7-405(1)(b)). Check the statute before you rely on these dates.

Does Mississippi require a preliminary notice?

No general preliminary notice requirement was found. On commercial work, contractors and first-tier subs give no notice before work. A commercial sub-subcontractor must give the GC written notice within 30 days of starting work (§ 85-7-407(2)). Check this point in the statute. A residential sub gives the owner a 10-day Pre-Lien Notice (§ 85-7-409).

Sources

Confidence: medium. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.