Utah Lien Waiver Form & Requirements

What a contractor, sub or supplier in Utah needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make an Utah lien waiver - free Calculate your Utah lien deadlines

Is there a required Utah lien waiver form?

Yes. Utah sets out the waiver wording in its statute (Utah Code 38-1a-802). The forms are: Conditional Waiver and Release Upon Progress Payment; Unconditional Waiver and Release Upon Progress Payment; Conditional Waiver and Release Upon Final Payment; Unconditional Waiver and Release Upon Final Payment. A waiver that does not follow the statute may not count.

A waiver must substantially follow the statutory form. A contract cannot waive lien rights in advance. Check this point in the statute.

Statute: Utah Code 38-1a-802

Does an Utah lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: Utah Code 38-1a-802

Conditional vs unconditional in Utah

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

In Utah the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.

Utah mechanics lien deadlines

StepDeadlineStatute
Preliminary notice20 days after first furnishing (the first day you worked or delivered)
File a preliminary notice on the State Construction Registry within 20 days after you first furnish work.
Utah Code 38-1a-501
Lien filing - general contractor180 days after final completion of the project
Record the notice of construction lien within 180 days after final completion of the original contract if no notice of completion is filed. If a notice of completion is filed, record within 90 days after it, but never later than 180 days after final completion.
Utah Code 38-1a-502(1)(a)
Lien filing - subcontractor180 days after final completion of the project
The same rule applies. A sub that does substantial work after the certificate of occupancy or final inspection has 180 days after final completion of its own work.
Utah Code 38-1a-502(1)
Suit to enforce the lien180 days after the lien being recorded
File the lawsuit within 180 days after filing the notice of construction lien. If a bankruptcy stay applies, file within 90 days after the stay lifts.
Utah Code 38-1a-701(2)

Who gives notice: Lien claimants, including subs and suppliers.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Utah

If the owner of an owner-occupied home paid in full, the home may be protected under the Residence Lien Restriction and Lien Recovery Fund Act.

Frequently asked

Is there a required Utah lien waiver form?

Yes. Utah sets out the waiver wording in its statute (Utah Code 38-1a-802). The forms are: Conditional Waiver and Release Upon Progress Payment; Unconditional Waiver and Release Upon Progress Payment; Conditional Waiver and Release Upon Final Payment; Unconditional Waiver and Release Upon Final Payment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.

Does an Utah lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: Utah Code 38-1a-802. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Utah?

General contractor: 180 days after final completion of the project (Utah Code 38-1a-502(1)(a)). Subcontractor: 180 days after final completion of the project (Utah Code 38-1a-502(1)). Check the statute before you rely on these dates.

Does Utah require a preliminary notice?

Yes for the parties the statute names: 20 days after first furnishing (the first day you worked or delivered) (Utah Code 38-1a-501). Lien claimants, including subs and suppliers.

Sources

Confidence: medium. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.