Nevada Lien Waiver Form & Requirements

What a contractor, sub or supplier in Nevada needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make a Nevada lien waiver - free Calculate your Nevada lien deadlines

Is there a required Nevada lien waiver form?

Yes. Nevada sets out the waiver wording in its statute (NRS 108.2457). The forms are: Conditional Waiver and Release Upon Progress Payment; Unconditional Waiver and Release Upon Progress Payment; Conditional Waiver and Release Upon Final Payment; Unconditional Waiver and Release Upon Final Payment. A waiver that does not follow the statute may not count.

A waiver cannot be enforced unless it uses the statute's form for that situation. The lien claimant or its agent signs it. A waiver signed before the work is done is void. No notary is required.

Statute: NRS 108.2457

Does a Nevada lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: NRS 108.2457

Conditional vs unconditional in Nevada

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

In Nevada the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.

Nevada mechanics lien deadlines

StepDeadlineStatute
Preliminary notice31 days after first furnishing (the first day you worked or delivered)
You may give a notice of right to lien any time after first furnishing. It covers work done in the 31 days before the notice and everything after. Give it within 31 days of first furnishing to protect all your work.
NRS 108.245(1), (6)
Lien filing - general contractor90 days after completion of the work
Record the lien within 90 days after the latest of completion, last furnishing and the other listed events. If a valid notice of completion is recorded and served, the deadline is 40 days after that notice.
NRS 108.226(1)
Lien filing - subcontractor90 days after completion of the work
Subs have the same deadline, including the shorter 40 days after a notice of completion.
NRS 108.226(1)
Suit to enforce the lien6 months after the lien being recorded
File suit within 6 months after the lien is recorded, unless a written extension is recorded.
NRS 108.233(1)

Who gives notice: Subs and suppliers who have no direct contract with the owner.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Nevada

Residential notice rules are different.

Frequently asked

Is there a required Nevada lien waiver form?

Yes. Nevada sets out the waiver wording in its statute (NRS 108.2457). The forms are: Conditional Waiver and Release Upon Progress Payment; Unconditional Waiver and Release Upon Progress Payment; Conditional Waiver and Release Upon Final Payment; Unconditional Waiver and Release Upon Final Payment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.

Does a Nevada lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: NRS 108.2457. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Nevada?

General contractor: 90 days after completion of the work (NRS 108.226(1)). Subcontractor: 90 days after completion of the work (NRS 108.226(1)). Check the statute before you rely on these dates.

Does Nevada require a preliminary notice?

Yes for the parties the statute names: 31 days after first furnishing (the first day you worked or delivered) (NRS 108.245(1), (6)). Subs and suppliers who have no direct contract with the owner.

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.

All states

More free tools
Lien Waiver GeneratorConditional and unconditional, progress and final Lien Deadline CalculatorYour notice and filing dates by state Retainage CalculatorStep-downs and what is held