BuildProofLien guide Free tools BuildProof.com

Arizona Lien Waiver Form & Requirements

What a contractor, sub or supplier in Arizona needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make an Arizona lien waiver - free Calculate your Arizona lien deadlines

Is there a required Arizona lien waiver form?

Yes. Arizona sets out the waiver wording in its statute (A.R.S. 33-1008). The forms are: Conditional Waiver and Release on Progress Payment; Unconditional Waiver and Release on Progress Payment; Conditional Waiver and Release on Final Payment; Unconditional Waiver and Release on Final Payment. A waiver that does not follow the statute may not count.

A waiver is enforceable only if it substantially follows the statutory form and the claimant or its agent signs it. A waiver given in advance in a contract is unenforceable.

Statute: A.R.S. 33-1008

Does an Arizona lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: A.R.S. 33-1008

Conditional vs unconditional in Arizona

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

In Arizona the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.

Arizona mechanics lien deadlines

StepDeadlineStatute
Preliminary notice20 days after first furnishing (the first day you worked or delivered)
Send the preliminary 20-day notice within 20 days after you first furnish to the jobsite. A late notice covers only work done from 20 days before you gave it.
A.R.S. 33-992.01
Lien filing - general contractor120 days after completion of the work
File within 120 days after completion, or within 60 days after a recorded notice of completion.
A.R.S. 33-993
Lien filing - subcontractor120 days after completion of the work
File within 120 days after completion, or within 60 days after a recorded notice of completion. If the notice of completion was not mailed to you, you have 120 days from completion.
A.R.S. 33-993
Suit to enforce the lien6 months after the lien being recorded
File suit within 6 months after recording, and record a notice of pendency.
A.R.S. 33-998

Who gives notice: Everyone who furnishes labor, services, materials or equipment, except those with a direct contract with the owner and wage laborers. Send it to the owner, the original contractor, the construction lender and whoever hired you.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Arizona

On an owner-occupied home, only those with a direct contract with the owner-occupant can file a lien.

Frequently asked

Is there a required Arizona lien waiver form?

Yes. Arizona sets out the waiver wording in its statute (A.R.S. 33-1008). The forms are: Conditional Waiver and Release on Progress Payment; Unconditional Waiver and Release on Progress Payment; Conditional Waiver and Release on Final Payment; Unconditional Waiver and Release on Final Payment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.

Does an Arizona lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: A.R.S. 33-1008. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Arizona?

General contractor: 120 days after completion of the work (A.R.S. 33-993). Subcontractor: 120 days after completion of the work (A.R.S. 33-993). Check the statute before you rely on these dates.

Does Arizona require a preliminary notice?

Yes for the parties the statute names: 20 days after first furnishing (the first day you worked or delivered) (A.R.S. 33-992.01). Everyone who furnishes labor, services, materials or equipment, except those with a direct contract with the owner and wage laborers. Send it to the owner, the original contractor, the construction lender and whoever hired you.

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.

All states

More free tools
Lien Waiver GeneratorConditional and unconditional, progress and final Lien Deadline CalculatorYour notice and filing dates by state Retainage CalculatorStep-downs and what is held