Is there a required Massachusetts lien waiver form?
Yes. Massachusetts sets out the waiver wording in its statute (M.G.L. c. 254 § 32). The forms are: Partial Waiver and Subordination of Lien. A waiver that does not follow the statute may not count.
A promise not to file a notice of contract or enforce a lien is void. The exception is a waiver given for an interim or final payment received. Anyone who filed a notice of contract must give partial waivers 'substantially in the following form with no material deviation therefrom' (§ 32(4)). The form is signed under the penalties of perjury. No notary is needed. There is no statutory final waiver form.
Statute: M.G.L. c. 254 § 32
Does a Massachusetts lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: M.G.L. c. 254 § 32
Conditional vs unconditional in Massachusetts
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
In Massachusetts the statute prescribes the waiver wording, so use that form. More on conditional vs unconditional.
Massachusetts mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 30 days after first furnishing (the first day you worked or delivered) A lower-tier party with no contract with the GC sends the GC a notice of identification by certified mail within 30 days after starting work. Without it, the lien is capped at the subcontract amount. | M.G.L. c. 254 § 4 |
| Lien filing - general contractor | 60 days after a notice of substantial completion File the notice of contract by the earliest of: 60 days after the notice of substantial completion is recorded, 90 days after a notice of termination is recorded, or 90 days after the last day of work. Then file the statement of account by the earliest of: 90 days after the notice of substantial completion, 120 days after a notice of termination, or 120 days after the last work. | M.G.L. c. 254 §§ 2, 8 |
| Lien filing - subcontractor | 60 days after a notice of substantial completion Subs have the same notice-of-contract deadlines as the GC: 60 days after the notice of substantial completion, 90 days after termination, or 90 days after last work. The § 8 statement of account deadlines follow. | M.G.L. c. 254 §§ 4, 8 |
| Suit to enforce the lien | 90 days after the statement of account being recorded File suit within 90 days after the statement of account is filed (§ 11). Record an attested copy of the complaint within 30 days after the suit starts, or the lien dissolves (§ 5). | M.G.L. c. 254 §§ 5, 11 |
Who gives notice: Subs and suppliers with no direct contract with the GC.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in Massachusetts
Separate rules apply to owner-occupied 1–4 family homes.
Frequently asked
Is there a required Massachusetts lien waiver form?
Yes. Massachusetts sets out the waiver wording in its statute (M.G.L. c. 254 § 32). The forms are: Partial Waiver and Subordination of Lien. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.
Does a Massachusetts lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: M.G.L. c. 254 § 32. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in Massachusetts?
General contractor: 60 days after a notice of substantial completion (M.G.L. c. 254 §§ 2, 8). Subcontractor: 60 days after a notice of substantial completion (M.G.L. c. 254 §§ 4, 8). Check the statute before you rely on these dates.
Does Massachusetts require a preliminary notice?
Yes for the parties the statute names: 30 days after first furnishing (the first day you worked or delivered) (M.G.L. c. 254 § 4). Subs and suppliers with no direct contract with the GC.
Sources
- https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section32
- https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section2
- https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section4
- https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section5
- https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section8
- https://malegislature.gov/Laws/GeneralLaws/PartIII/TitleIV/Chapter254/Section11
Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.