Georgia Lien Waiver Form & Requirements
What a contractor, sub or supplier in Georgia needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required Georgia lien waiver form?
Yes. Georgia sets out the waiver wording in its statute (O.C.G.A. § 44-14-366). The forms are: Interim Waiver and Release Upon Payment; Waiver and Release of Lien and Payment Bond Rights Upon Final Payment; Affidavit of Nonpayment. A waiver that does not follow the statute may not count.
Waivers must closely follow the statutory forms (SB 315, effective 1/1/2021). A signed waiver is binding unless the claimant files an Affidavit of Nonpayment within 60 days. Check this point in the statute. Whether a notary is required is not confirmed. Check this point in the statute.
Statute: O.C.G.A. § 44-14-366
Does a Georgia lien waiver need to be notarized?
Unclear. The statute does not settle it - check before you sign.
Statute: O.C.G.A. § 44-14-366
Conditional vs unconditional in Georgia
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
In Georgia the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.
Georgia mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 30 days after first furnishing (the first day you worked or delivered) Send a Notice to Contractor within 30 days after you first supply work or materials, or after the Notice of Commencement is filed, whichever is later. It is required only when a Notice of Commencement was filed. Check this point in the statute. | O.C.G.A. § 44-14-361.5 |
| Lien filing - general contractor | 90 days after last furnishing (the last day you worked or delivered) File within 90 days after you finish your work or last supply materials. Check this point in the statute. | O.C.G.A. § 44-14-361.1(a)(2) |
| Lien filing - subcontractor | 90 days after last furnishing (the last day you worked or delivered) The same 90-day rule as the GC. Check this point in the statute. | O.C.G.A. § 44-14-361.1(a)(2) |
| Suit to enforce the lien | 365 days after the lien being recorded File suit within 365 days after filing the lien. File a notice that the suit has started within 30 days after filing suit. Check this point in the statute. | O.C.G.A. § 44-14-361.1(a)(3) |
Who gives notice: Subs and suppliers with no direct contract with the contractor, when a Notice of Commencement has been filed.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in Georgia
The basic deadlines are the same. Differences for homes were not reviewed. Check this point in the statute.
Frequently asked
Is there a required Georgia lien waiver form?
Yes. Georgia sets out the waiver wording in its statute (O.C.G.A. § 44-14-366). The forms are: Interim Waiver and Release Upon Payment; Waiver and Release of Lien and Payment Bond Rights Upon Final Payment; Affidavit of Nonpayment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.
Does a Georgia lien waiver need to be notarized?
Unclear. The statute does not settle it - check before you sign. Statute: O.C.G.A. § 44-14-366. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in Georgia?
General contractor: 90 days after last furnishing (the last day you worked or delivered) (O.C.G.A. § 44-14-361.1(a)(2)). Subcontractor: 90 days after last furnishing (the last day you worked or delivered) (O.C.G.A. § 44-14-361.1(a)(2)). Check the statute before you rely on these dates.
Does Georgia require a preliminary notice?
Yes for the parties the statute names: 30 days after first furnishing (the first day you worked or delivered) (O.C.G.A. § 44-14-361.5). Subs and suppliers with no direct contract with the contractor, when a Notice of Commencement has been filed.
Sources
- https://www.akerman.com/en/perspectives/georgia-owners-and-contractors-time-to-update-your-lien-waiver-forms-and-other-contract-provisions.html
- https://ncscredit.com/education-center/blog/georgias-interim-lien-waivers-payment
- https://law.justia.com/codes/georgia/title-44/chapter-14/article-8/part-3/section-44-14-361-1/
- https://www.legis.ga.gov/api/legislation/document/20072008/83358
- https://www.ncscredit.com/hubfs/uploads/resources/2021/02/Reference-Guide-Lien-Suit-Deadlines-for-Private-Projects.pdf
- https://ezel.ai/surveys/mechanics-lien-deadlines/georgia
Confidence: medium. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.