California Lien Waiver Form & Requirements
What a contractor, sub or supplier in California needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required California lien waiver form?
Yes. California sets out the waiver wording in its statute (Cal. Civ. Code 8132-8138). The forms are: Conditional Waiver and Release on Progress Payment; Unconditional Waiver and Release on Progress Payment; Conditional Waiver and Release on Final Payment; Unconditional Waiver and Release on Final Payment. A waiver that does not follow the statute may not count.
A waiver is void unless it is signed and substantially follows the statutory form. An unconditional waiver takes effect only once payment is actually received.
Statute: Cal. Civ. Code 8132-8138
Does a California lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: Cal. Civ. Code 8132-8138
Conditional vs unconditional in California
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
In California the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.
California mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 20 days after first furnishing (the first day you worked or delivered) Send the 20-day preliminary notice no later than 20 days after you first furnish work. A late notice covers work from 20 days before you served it, and after. | Cal. Civ. Code 8204 |
| Lien filing - general contractor | 90 days after completion of the work File after you finish your contract, and before the earlier of: 90 days after the whole project is complete, or 60 days after a recorded notice of completion or cessation. | Cal. Civ. Code 8412 |
| Lien filing - subcontractor | 90 days after completion of the work File after you stop work, and before the earlier of: 90 days after the whole project is complete, or 30 days after a recorded notice of completion or cessation. | Cal. Civ. Code 8414 |
| Suit to enforce the lien | 90 days after the lien being recorded File the foreclosure suit within 90 days after recording. A recorded credit agreement can extend this. | Cal. Civ. Code 8460 |
Who gives notice: Everyone except the direct contractor and laborers.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in California
The same forms and deadlines apply. Home improvement contract rules add notices to the owner.
Frequently asked
Is there a required California lien waiver form?
Yes. California sets out the waiver wording in its statute (Cal. Civ. Code 8132-8138). The forms are: Conditional Waiver and Release on Progress Payment; Unconditional Waiver and Release on Progress Payment; Conditional Waiver and Release on Final Payment; Unconditional Waiver and Release on Final Payment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.
Does a California lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: Cal. Civ. Code 8132-8138. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in California?
General contractor: 90 days after completion of the work (Cal. Civ. Code 8412). Subcontractor: 90 days after completion of the work (Cal. Civ. Code 8414). Check the statute before you rely on these dates.
Does California require a preliminary notice?
Yes for the parties the statute names: 20 days after first furnishing (the first day you worked or delivered) (Cal. Civ. Code 8204). Everyone except the direct contractor and laborers.
Sources
- https://codes.findlaw.com/ca/civil-code/civ-sect-8414/
- https://codes.findlaw.com/ca/civil-code/civ-sect-8412/
- https://codes.findlaw.com/ca/civil-code/civ-sect-8460/
- https://codes.findlaw.com/ca/civil-code/civ-sect-8132/
- https://codes.findlaw.com/ca/civil-code/civ-sect-8204/
Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.