Florida Lien Waiver Form & Requirements
What a contractor, sub or supplier in Florida needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required Florida lien waiver form?
Yes. Florida sets out the waiver wording in its statute (Fla. Stat. 713.20). The forms are: Waiver and Release of Lien Upon Progress Payment; Waiver and Release of Lien Upon Final Payment. A waiver that does not follow the statute may not count.
A waiver 'may be' substantially in the statutory form. No one may require a lienor to use a different form (713.20(6)). A waiver that does not follow the form is still enforceable on its own terms (713.20(8)). A waiver signed in advance is unenforceable (713.20(2)). The forms have no notary block.
Statute: Fla. Stat. 713.20
Does a Florida lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: Fla. Stat. 713.20
Conditional vs unconditional in Florida
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
In Florida the statute prescribes the waiver wording, so use the statutory form for the type you mean. More on conditional vs unconditional.
Florida mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 45 days after first furnishing (the first day you worked or delivered) Serve the Notice to Owner before you start, or within 45 days after you first supply work or materials. It must also go out before the owner makes final payment. | Fla. Stat. 713.06(2) |
| Lien filing - general contractor | 90 days after last furnishing (the last day you worked or delivered) Record within 90 days after you last supply work or materials, or after termination if that is earlier (713.07(4)). Deliver the contractor's final payment affidavit at least 5 days before filing suit. | Fla. Stat. 713.08(5); 713.06(3)(d) |
| Lien filing - subcontractor | 90 days after last furnishing (the last day you worked or delivered) Within 90 days after you last supply work or materials. | Fla. Stat. 713.08(5) |
| Suit to enforce the lien | 12 months after the lien being recorded File suit within 1 year after recording the lien or an amended claim. If the owner records a Notice of Contest of Lien, you have only 60 days from when it is served. | Fla. Stat. 713.22 |
Who gives notice: Subcontractors, sub-subs and suppliers with no direct contract with the owner. Laborers do not need to send it.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in Florida
Residential work adds required disclosures to the owner. The deadlines are the same.
Frequently asked
Is there a required Florida lien waiver form?
Yes. Florida sets out the waiver wording in its statute (Fla. Stat. 713.20). The forms are: Waiver and Release of Lien Upon Progress Payment; Waiver and Release of Lien Upon Final Payment. A waiver that does not follow the statute may not count. This is a reference to check, not legal advice.
Does a Florida lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: Fla. Stat. 713.20. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in Florida?
General contractor: 90 days after last furnishing (the last day you worked or delivered) (Fla. Stat. 713.08(5); 713.06(3)(d)). Subcontractor: 90 days after last furnishing (the last day you worked or delivered) (Fla. Stat. 713.08(5)). Check the statute before you rely on these dates.
Does Florida require a preliminary notice?
Yes for the parties the statute names: 45 days after first furnishing (the first day you worked or delivered) (Fla. Stat. 713.06(2)). Subcontractors, sub-subs and suppliers with no direct contract with the owner. Laborers do not need to send it.
Sources
- https://www.flsenate.gov/Laws/Statutes/2024/713.08
- https://www.flsenate.gov/Laws/Statutes/2024/713.22
- https://www.flsenate.gov/Laws/Statutes/2024/713.20
- https://www.flsenate.gov/Laws/Statutes/2024/713.06
Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
BuildProof