New York Lien Law Section 22: the building loan contract filing

A New York construction lender's priority over mechanics' liens depends on a filing most project teams never see. This guide covers what Section 22 requires, and why it belongs in every draw review.

What Section 22 requires

A building loan contract, and any modification of it, must be in writing and acknowledged. It is filed with the clerk of the county where any part of the land lies, on or before the date the building loan mortgage is recorded. The statute says it is not filed in a register's office. In New York City the filing fee is $50; elsewhere in the state it is $25.

The borrower's sworn statement

The borrower verifies the contract under oath. The statement shows three things: the consideration paid or to be paid for the loan, the other expenses incurred or to be incurred in connection with it, and the net sum available to the borrower for the improvement. Lawyers call this the Section 22 affidavit. The net sum is the number a draw reviewer should know, because it is the figure the public record says is available to build with.

Modifications: the ten-day rule

A modification made after the original filing must itself be filed within ten days after it is executed. A modification does not cut back the rights of someone who furnished labor or materials before it was filed; those rights are measured by the original contract. The statute also says that an assignment of loan funds under Section 26, or a payment to that assignee, is not a modification.

What is at stake: priority

If the contract is not filed as Section 22 requires, the parties' interest in the property is subject to the lien of a person who later files a notice of lien. Section 13 ties the building loan mortgage's priority over mechanics' liens to two conditions: the trust fund covenant in Section 13(3) appears in the mortgage or the building loan contract, and the contract is filed under Section 22. Under that covenant the borrower holds the right to receive advances as a trust fund, to be applied first to the cost of the improvement.

Why it belongs in the draw review

The filing happens once at closing. The facts it describes keep moving. Our recommended practice is to carry the filed net sum into the draw file and reconcile every advance to it. When a change order, a budget reallocation or a loan increase alters what the filed contract says, flag it for the lender's counsel before the next advance. Whether a given change is a modification that must be filed is a legal question. The reviewer's job is to make sure counsel is asked while the ten days are still running.

Example: a budget that moved

Assume a filed contract shows a net sum of $8.2 million for the improvement. By the sixth draw, approved change orders have added $640,000 of hard cost and the borrower has asked to move $300,000 from contingency to interest reserve. Each draw package may be complete and every invoice supported. The open question is separate: does the loan budget still match the filed contract, and has anyone asked counsel whether an amendment and a new filing are needed? This is an illustrative control question, not legal advice.

Keep this handy

Review checklist

  • Filed building loan contract and Section 22 affidavit are in the draw file
  • Net sum available for the improvement is reconciled to advances to date
  • Approved changes and reallocations since the last draw are listed for counsel
  • Date of any executed amendment is recorded, with its filing date

Use your browser’s Print command to save this guide as a PDF.

Sources & scope

The statutory points above come from the text of the statute. The practice recommendations and the example are BuildProof’s editorial suggestions. The executed loan documents, applicable law and the lender's counsel control.

Educational guidance only. It is not legal advice and does not replace project-specific advice from a New York attorney.

Put the process into practice

See what is holding each draw.

BuildProof checks each requisition against its backup, waivers and insurance, and names what is still open before you fund.

BuildProof tools are independent worksheets, not licensed AIA documents.