What Is Retainage?
Retainage is part of each construction payment that the owner holds back until the work is finished. It is the contractor's money, held as security.
How it works
Each month the contractor bills for the work done. The owner pays that amount minus a percentage, and keeps the percentage. The general contractor usually does the same to its subs. The held amounts add up over the job and are paid out at the end, once the work is complete and the paperwork is in.
The point is leverage. With money still held, the owner has a reason for the contractor to come back and finish the punch list, fix defects and hand over closeout documents.
Typical rates
Ten percent of each payment is common. Five percent is also common, and many contracts start at ten and drop to five at the halfway point or at substantial completion. That drop is called a step-down. Some states cap retainage on private or public jobs. Check your state's law and your contract; a rate above a statutory cap may not be enforceable.
Step-downs
A step-down can work two ways. Applied going forward, the lower rate covers only new work and the money already held stays held. Applied to everything, the lower rate is recalculated on all work to date, which releases money right away. The contract wording decides which one applies. The free retainage calculator shows both.
Release
Retainage is usually released in one or two steps: most of it at substantial completion, the rest at final completion or once the lien period has closed. Release often needs a final application, a final lien waiver from the contractor and its subs, closeout documents and sometimes the lender's sign-off. A sub may get its retainage early if its trade finished early and the contract allows it.
Retainage and lien waivers
A final lien waiver often gives up the right to claim retainage. If retainage is still owed, list it as an exception on the waiver. See conditional vs unconditional waivers.
Common problems
- Retainage held from a sub at a higher rate than the owner holds from the GC.
- Release delayed for months after the work is finished, waiting on closeout paperwork.
- Arithmetic errors after a step-down, especially when it is applied retroactively.
- A final waiver signed with retainage still owed and no exception.
A quick example
A sub has a $200,000 subcontract with 10% retainage. Halfway through, it has billed $100,000 and been paid $90,000; $10,000 is held. If the contract steps down to 5% going forward, the next $100,000 of work has $5,000 held, so $15,000 is held at the end. If the step-down applies to everything, the held amount on the first half drops to $5,000 right away and $5,000 is released, so $10,000 is held at the end. Same contract, different words, $5,000 apart.
Tracking it
Keep retainage held, released and still owed on every application, for every sub, and check that the totals match what the owner is holding from the general contractor. Mismatches are easiest to fix the month they appear.
Frequently asked
What is retainage in construction?
A percentage of each progress payment held back by the owner (or GC) until the work is finished, as security.
What is a typical retainage rate?
Commonly 10%, often stepping down to 5% at the halfway point or substantial completion. Some states cap it.
When is retainage released?
Usually at substantial completion and final completion, once the final paperwork and waivers are in, depending on the contract and state law.
BuildProof