South Dakota Lien Waiver Form & Requirements
What a contractor, sub or supplier in South Dakota needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required South Dakota lien waiver form?
No required statutory form was found for South Dakota (SDCL ch. 44-9 (no statutory waiver form)). Parties can use their own wording, but it should be clear about the payment, the period and the amount.
South Dakota has no statutory waiver form. General contract rules apply.
Statute: SDCL ch. 44-9 (no statutory waiver form)
Does a South Dakota lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: SDCL ch. 44-9 (no statutory waiver form)
Conditional vs unconditional in South Dakota
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
South Dakota has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.
South Dakota mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | No general requirement found | - |
| Lien filing - general contractor | 120 days after last furnishing (the last day you worked or delivered) The lien ends 120 days after the last work unless you file a statement with the register of deeds within that time. | SDCL 44-9-15 |
| Lien filing - subcontractor | 120 days after last furnishing (the last day you worked or delivered) The same 120-day rule applies, counted from the claimant's last furnishing. | SDCL 44-9-15 |
| Suit to enforce the lien | not confirmed - check the statute You generally have 6 years after filing to sue. Check this point in the statute. But if the owner serves a written demand, you must sue within 30 days of being served or you lose the lien. | SDCL 44-9-26 |
Who gives notice: Most claimants owe no preliminary notice. Only on a project with a recorded Notice of Project Commencement (SDCL 44-9-50, 44-9-51), a sub-subcontractor or a supplier to a subcontractor must mail a notice of furnishing to the named contractor, copying the owner, within 60 days after its last furnishing, and attach the mailing receipt to its lien (SDCL 44-9-53).
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in South Dakota
An earlier note said the 44-9-53 notice applied only to residential work and was due 10 days before filing. The statute says 60 days after the last work and does not mention residential work. Check this point in the statute.
Frequently asked
Is there a required South Dakota lien waiver form?
No required statutory form was found for South Dakota (SDCL ch. 44-9 (no statutory waiver form)). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.
Does a South Dakota lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: SDCL ch. 44-9 (no statutory waiver form). This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in South Dakota?
General contractor: 120 days after last furnishing (the last day you worked or delivered) (SDCL 44-9-15). Subcontractor: 120 days after last furnishing (the last day you worked or delivered) (SDCL 44-9-15). Check the statute before you rely on these dates.
Does South Dakota require a preliminary notice?
No general preliminary notice requirement was found. Most claimants owe no preliminary notice. Only on a project with a recorded Notice of Project Commencement (SDCL 44-9-50, 44-9-51), a sub-subcontractor or a supplier to a subcontractor must mail a notice of furnishing to the named contractor, copying the owner, within 60 days after its last furnishing, and attach the mailing receipt to its lien (SDCL 44-9-53).
Sources
- https://media.oldrepublictitle.com/commercial/national/ebook/state-law-summary/files/basic-html/page47.html
- https://sdlegislature.gov/Statutes/44-9-15
- https://sdlegislature.gov/api/Statutes/44-9-15.html
- https://sdlegislature.gov/api/Statutes/44-9-26.html
- https://sdlegislature.gov/api/Statutes/44-9-53.html
Confidence: medium. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
BuildProof