Is there a required Rhode Island lien waiver form?

No required statutory form was found for Rhode Island (R.I. Gen. Laws ch. 34-28). Parties can use their own wording, but it should be clear about the payment, the period and the amount.

Rhode Island has no statutory waiver form that we could confirm. Check this point in the statute.

Statute: R.I. Gen. Laws ch. 34-28

Does a Rhode Island lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: R.I. Gen. Laws ch. 34-28

Conditional vs unconditional in Rhode Island

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

Rhode Island has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.

Rhode Island mechanics lien deadlines

StepDeadlineStatute
Preliminary noticeNo general requirement found-
Lien filing - general contractor200 days after last furnishing (the last day you worked or delivered)
Record the notice of intention before, or within 200 days after, the work is done or the materials are furnished.
R.I. Gen. Laws 34-28-4
Lien filing - subcontractor200 days after last furnishing (the last day you worked or delivered)
Subcontractors have the same deadline as the GC.
R.I. Gen. Laws 34-28-4
Suit to enforce the lien40 days after the lien being recorded
File the complaint and the lis pendens within 40 days after recording the notice of intention. You may file the complaint the same day as the lis pendens or up to 7 days later.
R.I. Gen. Laws 34-28-10

Who gives notice: Lower tiers do not send a preliminary notice. Under 34-28-4.1, a party that contracts directly with the owner (not a material supplier) must give a notice of possible lien before starting work or delivering materials. It goes in the contract or by certified mail. If the party does not give it, that party must indemnify the owner against liens from parties with no contract with the owner. This rule is not limited to residential work.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Rhode Island

The 34-28-4.1 notice of possible lien applies to direct contractors on all work, not only residential work.

Frequently asked

Is there a required Rhode Island lien waiver form?

No required statutory form was found for Rhode Island (R.I. Gen. Laws ch. 34-28). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.

Does a Rhode Island lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: R.I. Gen. Laws ch. 34-28. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Rhode Island?

General contractor: 200 days after last furnishing (the last day you worked or delivered) (R.I. Gen. Laws 34-28-4). Subcontractor: 200 days after last furnishing (the last day you worked or delivered) (R.I. Gen. Laws 34-28-4). Check the statute before you rely on these dates.

Does Rhode Island require a preliminary notice?

No general preliminary notice requirement was found. Lower tiers do not send a preliminary notice. Under 34-28-4.1, a party that contracts directly with the owner (not a material supplier) must give a notice of possible lien before starting work or delivering materials. It goes in the contract or by certified mail. If the party does not give it, that party must indemnify the owner against liens from parties with no contract with the owner. This rule is not limited to residential work.

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.