Pennsylvania Lien Waiver Form & Requirements
What a contractor, sub or supplier in Pennsylvania needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required Pennsylvania lien waiver form?
No required statutory form was found for Pennsylvania (49 P.S. §1401). Parties can use their own wording, but it should be clear about the payment, the period and the amount.
Pennsylvania has no statutory waiver form. Since the 2006 amendments, waivers signed in advance are generally not enforceable, with limited exceptions such as some residential work. A waiver given in exchange for payment is enforceable.
Statute: 49 P.S. §1401
Does a Pennsylvania lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: 49 P.S. §1401
Conditional vs unconditional in Pennsylvania
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
Pennsylvania has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.
Pennsylvania mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 45 days after first furnishing (the first day you worked or delivered) File a Notice of Furnishing in the State Construction Notices Directory within 45 days of first furnishing. This applies only on projects of $1.5 million or more where the owner has posted a Notice of Commencement. Check this point in the statute. | 49 P.S. §1501 |
| Lien filing - general contractor | 6 months after completion of the work File the claim within 6 months after your work is complete. | 49 P.S. §1502 |
| Lien filing - subcontractor | 6 months after completion of the work Subcontractors also have 6 months. They must give a formal notice of intent at least 30 days before filing. Check this point in the statute. | 49 P.S. §1501(b), §1502 |
| Suit to enforce the lien | 24 months after the lien being recorded Start the action within 2 years after filing. | 49 P.S. §1701 |
Who gives notice: Subcontractors, when a Notice of Commencement has been filed.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in Pennsylvania
Residential work has different limits on subcontractor liens and different waiver rules.
Frequently asked
Is there a required Pennsylvania lien waiver form?
No required statutory form was found for Pennsylvania (49 P.S. §1401). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.
Does a Pennsylvania lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: 49 P.S. §1401. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in Pennsylvania?
General contractor: 6 months after completion of the work (49 P.S. §1502). Subcontractor: 6 months after completion of the work (49 P.S. §1501(b), §1502). Check the statute before you rely on these dates.
Does Pennsylvania require a preliminary notice?
Yes for the parties the statute names: 45 days after first furnishing (the first day you worked or delivered) (49 P.S. §1501). Subcontractors, when a Notice of Commencement has been filed.
Sources
- https://www.legis.state.pa.us/cfdocs/legis/LI/uconsCheck.cfm?txtType=HTM&yr=1963&sessInd=0&smthLwInd=0&act=497&chpt=5
- https://www.palegis.us/statutes/unconsolidated/law-information/view-statute?SESSYR=1963&SESSIND=0&ACTNUM=497&SMTHLWIND=&CHPT=5&SCTN=&SUBSCTN=
- https://codes.findlaw.com/pa/title-49-ps-mechanics-liens/pa-st-sect-49-1502/
- https://blogs.duanemorris.com/constructionlaw/?p=118
- https://media.oldrepublictitle.com/commercial/national/ebook/state-law-summary/files/basic-html/page42.html
Confidence: medium. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
BuildProof