Ohio Lien Waiver Form & Requirements
What a contractor, sub or supplier in Ohio needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required Ohio lien waiver form?
No required statutory form was found for Ohio (O.R.C. ch. 1311). Parties can use their own wording, but it should be clear about the payment, the period and the amount.
Ohio has no required statutory waiver form. Use a written waiver or release tied to the payment. Check this point in the statute.
Statute: O.R.C. ch. 1311
Does an Ohio lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: O.R.C. ch. 1311
Conditional vs unconditional in Ohio
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
Ohio has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.
Ohio mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 21 days after first furnishing (the first day you worked or delivered) When a Notice of Commencement has been recorded, send a Notice of Furnishing to the owner and GC within 21 days of first furnishing, unless an extended period under 1311.04(I) or (J) applies. A late notice protects the lien only for work or materials furnished from 21 days before you served it. It does not revive earlier rights. | O.R.C. 1311.05 |
| Lien filing - general contractor | 75 days after last furnishing (the last day you worked or delivered) For commercial and all other liens not listed below, file the affidavit within 75 days of last furnishing. Residential is 60 days. Liens under 1311.021 (oil and gas wells) are 120 days. | O.R.C. 1311.06 |
| Lien filing - subcontractor | 75 days after last furnishing (the last day you worked or delivered) Subcontractors have the same deadline as the GC. | O.R.C. 1311.06 |
| Suit to enforce the lien | 72 months after the lien being recorded The lien lasts 6 years from filing the affidavit, or until judgment if suit starts within that time. The owner can force suit by serving a notice to commence. You must then sue within 60 days after service is complete, or the lien is void. | O.R.C. 1311.13, 1311.11 |
Who gives notice: Subcontractors and suppliers with no direct contract with the owner.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in Ohio
The residential lien deadline is 60 days. This covers a one- or two-family dwelling, or a residential condominium unit.
Frequently asked
Is there a required Ohio lien waiver form?
No required statutory form was found for Ohio (O.R.C. ch. 1311). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.
Does an Ohio lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: O.R.C. ch. 1311. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in Ohio?
General contractor: 75 days after last furnishing (the last day you worked or delivered) (O.R.C. 1311.06). Subcontractor: 75 days after last furnishing (the last day you worked or delivered) (O.R.C. 1311.06). Check the statute before you rely on these dates.
Does Ohio require a preliminary notice?
Yes for the parties the statute names: 21 days after first furnishing (the first day you worked or delivered) (O.R.C. 1311.05). Subcontractors and suppliers with no direct contract with the owner.
Sources
- https://codes.ohio.gov/ohio-revised-code/section-1311.06
- https://codes.ohio.gov/ohio-revised-code/section-1311.13
- https://codes.ohio.gov/ohio-revised-code/section-1311.05
- https://codes.ohio.gov/ohio-revised-code/section-1311.11
Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.