North Carolina Lien Waiver Form & Requirements

What a contractor, sub or supplier in North Carolina needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make a North Carolina lien waiver - free Calculate your North Carolina lien deadlines

Is there a required North Carolina lien waiver form?

No required statutory form was found for North Carolina (N.C.G.S. 44A-12(f)). Parties can use their own wording, but it should be clear about the payment, the period and the amount.

North Carolina has no statutory waiver form. Under 44A-12(f), an agreement to waive the right to file a claim of lien, made in anticipation of and in exchange for the award of a contract, is against public policy and cannot be enforced. You can still subordinate or release a lien.

Statute: N.C.G.S. 44A-12(f)

Does a North Carolina lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: N.C.G.S. 44A-12(f)

Conditional vs unconditional in North Carolina

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

North Carolina has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.

North Carolina mechanics lien deadlines

StepDeadlineStatute
Preliminary notice15 days after first furnishing (the first day you worked or delivered)
When a lien agent is named, the Notice to Lien Agent (filed on LiensNC) must reach the lien agent within 15 days of first furnishing. You may send it later, but a late notice does not protect you against a sale to a good-faith buyer, or a non-insider mortgage or deed of trust, recorded before it.
N.C.G.S. 44A-11.2
Lien filing - general contractor120 days after last furnishing (the last day you worked or delivered)
File the claim of lien within 120 days after the last furnishing of labor or materials at the site.
N.C.G.S. 44A-12
Lien filing - subcontractor120 days after last furnishing (the last day you worked or delivered)
Subcontractors also have 120 days. Lower tiers also use the subrogation lien and the notice of claim of lien upon funds.
N.C.G.S. 44A-12, 44A-23
Suit to enforce the lien180 days after last furnishing (the last day you worked or delivered)
File suit within 180 days after last furnishing. The clock runs from last furnishing, not from the date you filed the lien.
N.C.G.S. 44A-13

Who gives notice: Anyone claiming lien rights, including the GC, subs and suppliers, on projects with a named lien agent.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in North Carolina

A lien agent is not required for an owner's own residence, or for improvements under $40,000. Check this point in the statute.

Frequently asked

Is there a required North Carolina lien waiver form?

No required statutory form was found for North Carolina (N.C.G.S. 44A-12(f)). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.

Does a North Carolina lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: N.C.G.S. 44A-12(f). This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in North Carolina?

General contractor: 120 days after last furnishing (the last day you worked or delivered) (N.C.G.S. 44A-12). Subcontractor: 120 days after last furnishing (the last day you worked or delivered) (N.C.G.S. 44A-12, 44A-23). Check the statute before you rely on these dates.

Does North Carolina require a preliminary notice?

Yes for the parties the statute names: 15 days after first furnishing (the first day you worked or delivered) (N.C.G.S. 44A-11.2). Anyone claiming lien rights, including the GC, subs and suppliers, on projects with a named lien agent.

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.