BuildProofLien guide Free tools BuildProof.com

Missouri Lien Waiver Form & Requirements

What a contractor, sub or supplier in Missouri needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make a Missouri lien waiver - free Calculate your Missouri lien deadlines

Is there a required Missouri lien waiver form?

No required statutory form was found for Missouri (Mo. Rev. Stat. ch. 429 (no mandatory commercial form found)). Parties can use their own wording, but it should be clear about the payment, the period and the amount.

We found no required statutory waiver form for commercial work. Check this point in the statute.

Statute: Mo. Rev. Stat. ch. 429 (no mandatory commercial form found)

Does a Missouri lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: Mo. Rev. Stat. ch. 429 (no mandatory commercial form found)

Conditional vs unconditional in Missouri

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

Missouri has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.

Missouri mechanics lien deadlines

StepDeadlineStatute
Preliminary noticeNo general requirement found-
Lien filing - general contractor6 months after last furnishing (the last day you worked or delivered)
File the lien within 6 months after the debt accrues. In practice, that is the last furnishing. For rental equipment, you have 60 days after removal.
Mo. Rev. Stat. § 429.080
Lien filing - subcontractor6 months after last furnishing (the last day you worked or delivered)
Subs have the same 6 months, after giving the 10-day notice.
Mo. Rev. Stat. §§ 429.080, 429.100
Suit to enforce the lien6 months after the lien being recorded
File suit within 6 months after the lien is filed.
Mo. Rev. Stat. § 429.170

Who gives notice: Commercial work needs no early notice. Everyone except the original contractor must give the owner notice at least 10 days before filing the lien (§ 429.100). On residential projects, the GC must put a notice in the contract (§ 429.012).

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Missouri

On residential projects, the GC must put a notice in the contract (§ 429.012).

Frequently asked

Is there a required Missouri lien waiver form?

No required statutory form was found for Missouri (Mo. Rev. Stat. ch. 429 (no mandatory commercial form found)). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.

Does a Missouri lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: Mo. Rev. Stat. ch. 429 (no mandatory commercial form found). This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Missouri?

General contractor: 6 months after last furnishing (the last day you worked or delivered) (Mo. Rev. Stat. § 429.080). Subcontractor: 6 months after last furnishing (the last day you worked or delivered) (Mo. Rev. Stat. §§ 429.080, 429.100). Check the statute before you rely on these dates.

Does Missouri require a preliminary notice?

No general preliminary notice requirement was found. Commercial work needs no early notice. Everyone except the original contractor must give the owner notice at least 10 days before filing the lien (§ 429.100). On residential projects, the GC must put a notice in the contract (§ 429.012).

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.

All states

More free tools
Lien Waiver GeneratorConditional and unconditional, progress and final Lien Deadline CalculatorYour notice and filing dates by state Retainage CalculatorStep-downs and what is held