Minnesota Lien Waiver Form & Requirements

What a contractor, sub or supplier in Minnesota needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make a Minnesota lien waiver - free Calculate your Minnesota lien deadlines

Is there a required Minnesota lien waiver form?

No required statutory form was found for Minnesota (Minn. Stat. ch. 514 (no waiver form statute confirmed)). Parties can use their own wording, but it should be clear about the payment, the period and the amount.

We found no required statutory waiver form. Check this point in the statute. Ordinary waivers given in exchange for payment are used.

Statute: Minn. Stat. ch. 514 (no waiver form statute confirmed)

Does a Minnesota lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: Minn. Stat. ch. 514 (no waiver form statute confirmed)

Conditional vs unconditional in Minnesota

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

Minnesota has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.

Minnesota mechanics lien deadlines

StepDeadlineStatute
Preliminary notice45 days after first furnishing (the first day you worked or delivered)
A claimant with no direct contract with the owner gives the owner written notice within 45 days after first supplying labor or materials. This is not required for nonagricultural work that is wholly or partly nonresidential and adds more than 5,000 usable sq ft, or on property that already has more than 5,000 usable sq ft (§ 514.011 subd. 4c).
Minn. Stat. § 514.011 subd. 2, 4c
Lien filing - general contractor120 days after last furnishing (the last day you worked or delivered)
Record the lien statement within 120 days after doing the last of the work.
Minn. Stat. § 514.08 subd. 1
Lien filing - subcontractor120 days after last furnishing (the last day you worked or delivered)
Subs and suppliers have the same 120-day deadline.
Minn. Stat. § 514.08 subd. 1
Suit to enforce the lien12 months after last furnishing (the last day you worked or delivered)
Enforce the lien within 1 year after the date of the last item of the claim in the recorded lien statement.
Minn. Stat. § 514.12 subd. 3

Who gives notice: Subs and suppliers with no direct contract with the owner, unless the exemption applies. A GC puts its notice in its contract with the owner.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Minnesota

The pre-lien notice rules apply mostly to residential and small commercial work.

Frequently asked

Is there a required Minnesota lien waiver form?

No required statutory form was found for Minnesota (Minn. Stat. ch. 514 (no waiver form statute confirmed)). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.

Does a Minnesota lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: Minn. Stat. ch. 514 (no waiver form statute confirmed). This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Minnesota?

General contractor: 120 days after last furnishing (the last day you worked or delivered) (Minn. Stat. § 514.08 subd. 1). Subcontractor: 120 days after last furnishing (the last day you worked or delivered) (Minn. Stat. § 514.08 subd. 1). Check the statute before you rely on these dates.

Does Minnesota require a preliminary notice?

Yes for the parties the statute names: 45 days after first furnishing (the first day you worked or delivered) (Minn. Stat. § 514.011 subd. 2, 4c). Subs and suppliers with no direct contract with the owner, unless the exemption applies. A GC puts its notice in its contract with the owner.

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.