Illinois Lien Waiver Form & Requirements
What a contractor, sub or supplier in Illinois needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required Illinois lien waiver form?
No required statutory form was found for Illinois (770 ILCS 60 (no waiver form in the statute)). Parties can use their own wording, but it should be clear about the payment, the period and the amount.
Illinois has no mandatory waiver form. Before the owner pays the contractor, the contractor must give a sworn statement (770 ILCS 60/5). It is made under oath or by affidavit and lists everyone who supplied labor or materials and what each is owed.
Statute: 770 ILCS 60 (no waiver form in the statute)
Does an Illinois lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: 770 ILCS 60 (no waiver form in the statute)
Conditional vs unconditional in Illinois
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
Illinois has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.
Illinois mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | 90 days after last furnishing (the last day you worked or delivered) A sub or supplier must serve the owner (and lender) with written notice of its claim within 90 days after it completes its own work. On owner-occupied homes a 60-day notice from first furnishing applies instead. | 770 ILCS 60/24 |
| Lien filing - general contractor | 4 months after completion of the work To bind third parties, sue or record a sworn lien claim within 4 months after completion. Against the owner, you can file the claim up to 2 years after completion. | 770 ILCS 60/7 |
| Lien filing - subcontractor | 4 months after completion of the work Serve the 90-day notice (60/24), then record within 4 months after completion. | 770 ILCS 60/7; 60/24 |
| Suit to enforce the lien | 24 months after completion of the work Sue within 2 years after the contract is completed. If the owner sends a written demand, sue within 30 days or you lose the lien. | 770 ILCS 60/9; 60/34 |
Who gives notice: Subs and suppliers who have no direct contract with the owner
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in Illinois
On owner-occupied residential work, a sub may need to give notice within 60 days of first furnishing. This rule is not in the text of 60/24 that was read. Check this point in the statute.
Frequently asked
Is there a required Illinois lien waiver form?
No required statutory form was found for Illinois (770 ILCS 60 (no waiver form in the statute)). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.
Does an Illinois lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: 770 ILCS 60 (no waiver form in the statute). This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in Illinois?
General contractor: 4 months after completion of the work (770 ILCS 60/7). Subcontractor: 4 months after completion of the work (770 ILCS 60/7; 60/24). Check the statute before you rely on these dates.
Does Illinois require a preliminary notice?
Yes for the parties the statute names: 90 days after last furnishing (the last day you worked or delivered) (770 ILCS 60/24). Subs and suppliers who have no direct contract with the owner
Sources
- https://www.ilga.gov/legislation/ilcs/ilcs3.asp?ActID=2196&ChapterID=62
- https://ilga.gov/Documents/legislation/ilcs/documents/077000600K7.htm
- https://codes.findlaw.com/il/chapter-770-liens/il-st-sect-770-60-7/
- https://codes.findlaw.com/il/chapter-770-liens/il-st-sect-770-60-9/
- https://codes.findlaw.com/il/chapter-770-liens/il-st-sect-770-60-24/
- https://codes.findlaw.com/il/chapter-770-liens/il-st-sect-770-60-34/
- https://codes.findlaw.com/il/chapter-770-liens/il-st-sect-770-60-5/
- https://www.siteline.com/mechanics-lien-rights/illinois
Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.