District of Columbia Lien Waiver Form & Requirements
What a contractor, sub or supplier in District of Columbia needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.
Is there a required District of Columbia lien waiver form?
No required statutory form was found for District of Columbia (D.C. Code 40-301.01 et seq.). Parties can use their own wording, but it should be clear about the payment, the period and the amount.
D.C. has no required waiver form. Check this point in the statute.
Statute: D.C. Code 40-301.01 et seq.
Does a District of Columbia lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver.
Statute: D.C. Code 40-301.01 et seq.
Conditional vs unconditional in District of Columbia
A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.
District of Columbia has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.
District of Columbia mechanics lien deadlines
| Step | Deadline | Statute |
|---|---|---|
| Preliminary notice | No general requirement found | - |
| Lien filing - general contractor | 90 days after completion of the work Record the notice of intent during construction, or within 90 days after the project is completed or terminated, whichever comes first. | D.C. Code 40-301.02(a)(1) |
| Lien filing - subcontractor | 90 days after completion of the work The same as the GC: during construction, or within 90 days after the project is completed or terminated, whichever comes first. Give notice to the owner. | D.C. Code 40-301.02; 40-301.05 |
| Suit to enforce the lien | 180 days after the lien being recorded File suit within 180 days after recording the notice of intent. If you do not, the lien ends. | D.C. Code 40-303.13(a)(1)(A) |
Who gives notice: No preliminary notice. Instead, you record a notice of intent and serve it on the owner.
Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.
Residential work in District of Columbia
Check this point in the statute.
Frequently asked
Is there a required District of Columbia lien waiver form?
No required statutory form was found for District of Columbia (D.C. Code 40-301.01 et seq.). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.
Does a District of Columbia lien waiver need to be notarized?
No notary requirement was found in the statute for a waiver. Statute: D.C. Code 40-301.01 et seq.. This is a reference to check, not legal advice.
How long do I have to file a mechanics lien in District of Columbia?
General contractor: 90 days after completion of the work (D.C. Code 40-301.02(a)(1)). Subcontractor: 90 days after completion of the work (D.C. Code 40-301.02; 40-301.05). Check the statute before you rely on these dates.
Does District of Columbia require a preliminary notice?
No general preliminary notice requirement was found. No preliminary notice. Instead, you record a notice of intent and serve it on the owner.
Sources
- https://code.dccouncil.gov/us/dc/council/code/sections/40-301.02
- https://code.dccouncil.gov/us/dc/council/code/sections/40-303.13
Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.