BuildProofLien guide Free tools BuildProof.com

Colorado Lien Waiver Form & Requirements

What a contractor, sub or supplier in Colorado needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make a Colorado lien waiver - free Calculate your Colorado lien deadlines

Is there a required Colorado lien waiver form?

No required statutory form was found for Colorado (C.R.S. 38-22-101 et seq.). Parties can use their own wording, but it should be clear about the payment, the period and the amount.

Colorado has no required statutory waiver form.

Statute: C.R.S. 38-22-101 et seq.

Does a Colorado lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: C.R.S. 38-22-101 et seq.

Conditional vs unconditional in Colorado

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

Colorado has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.

Colorado mechanics lien deadlines

StepDeadlineStatute
Preliminary noticeNo general requirement found-
Lien filing - general contractor4 months after last furnishing (the last day you worked or delivered)
File within 4 months after your last labor or materials.
C.R.S. 38-22-109(5)
Lien filing - subcontractor4 months after last furnishing (the last day you worked or delivered)
File within 4 months after last furnishing. Laborers paid by the day or by the piece (no materials) have 2 months after the project is complete (38-22-109(4)).
C.R.S. 38-22-109(4)-(5)
Suit to enforce the lien6 months after last furnishing (the last day you worked or delivered)
File suit within 6 months after the last work or materials, or after the project is complete. The clock does not start at recording.
C.R.S. 38-22-110

Who gives notice: No preliminary notice. Every claimant must serve a notice of intent to lien on the owner and the prime contractor at least 10 days before filing (C.R.S. 38-22-109(3)).

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Colorado

An owner-occupant who paid the contractor in full has a defense.

Frequently asked

Is there a required Colorado lien waiver form?

No required statutory form was found for Colorado (C.R.S. 38-22-101 et seq.). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.

Does a Colorado lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: C.R.S. 38-22-101 et seq.. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Colorado?

General contractor: 4 months after last furnishing (the last day you worked or delivered) (C.R.S. 38-22-109(5)). Subcontractor: 4 months after last furnishing (the last day you worked or delivered) (C.R.S. 38-22-109(4)-(5)). Check the statute before you rely on these dates.

Does Colorado require a preliminary notice?

No general preliminary notice requirement was found. No preliminary notice. Every claimant must serve a notice of intent to lien on the owner and the prime contractor at least 10 days before filing (C.R.S. 38-22-109(3)).

Sources

Confidence: high. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.

All states

More free tools
Lien Waiver GeneratorConditional and unconditional, progress and final Lien Deadline CalculatorYour notice and filing dates by state Retainage CalculatorStep-downs and what is held