Alabama Lien Waiver Form & Requirements

What a contractor, sub or supplier in Alabama needs to know about lien waivers and lien deadlines, in plain words, with the statute for each point.

This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.
Make an Alabama lien waiver - free Calculate your Alabama lien deadlines

Is there a required Alabama lien waiver form?

No required statutory form was found for Alabama (Ala. Code 35-11-200 et seq. prescribes no waiver form). Parties can use their own wording, but it should be clear about the payment, the period and the amount.

Alabama has no statutory lien waiver form. Waivers are contracts, and courts judge them under general contract law.

Statute: Ala. Code 35-11-200 et seq. prescribes no waiver form

Does an Alabama lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver.

Statute: Ala. Code 35-11-200 et seq. prescribes no waiver form

Conditional vs unconditional in Alabama

A conditional waiver gives up lien rights only once the payment actually clears. Sign it when you send a bill or before the check arrives. An unconditional waiver gives up the rights the moment you sign, paid or not. Sign it only after the money is in your account.

Alabama has no required form, so read the waiver you are handed and check which type it is before you sign. More on conditional vs unconditional.

Alabama mechanics lien deadlines

StepDeadlineStatute
Preliminary noticeNo general requirement found-
Lien filing - general contractor6 months after last furnishing (the last day you worked or delivered)
An original contractor files within 6 months after it last furnishes work or materials. Check this point in the statute.
Ala. Code 35-11-215
Lien filing - subcontractor4 months after last furnishing (the last day you worked or delivered)
Everyone else (subs and suppliers) files within 4 months after last furnishing, after serving notice on the owner. Journeymen and day laborers have 30 days. Check this point in the statute.
Ala. Code 35-11-215; 35-11-210
Suit to enforce the lien6 months after the debt coming due
File suit within 6 months after the whole debt comes due. The clock does not start at recording.
Ala. Code 35-11-221

Who gives notice: Private commercial work needs no preliminary notice. Before filing a lien, a claimant without a direct contract with the owner must give the owner written notice of the claim (Ala. Code 35-11-210). This is a notice before the lien, not a preliminary notice. Check this point in the statute.

Deadlines are strict. Missing one usually ends the lien right for good. Count from the event the statute names, and check the statute for weekends, holidays and recording rules.

Residential work in Alabama

The same deadlines apply. Check the statute for rules on owner-occupied homes.

Frequently asked

Is there a required Alabama lien waiver form?

No required statutory form was found for Alabama (Ala. Code 35-11-200 et seq. prescribes no waiver form). Parties can use their own wording, but it should be clear about the payment, the period and the amount. This is a reference to check, not legal advice.

Does an Alabama lien waiver need to be notarized?

No notary requirement was found in the statute for a waiver. Statute: Ala. Code 35-11-200 et seq. prescribes no waiver form. This is a reference to check, not legal advice.

How long do I have to file a mechanics lien in Alabama?

General contractor: 6 months after last furnishing (the last day you worked or delivered) (Ala. Code 35-11-215). Subcontractor: 4 months after last furnishing (the last day you worked or delivered) (Ala. Code 35-11-215; 35-11-210). Check the statute before you rely on these dates.

Does Alabama require a preliminary notice?

No general preliminary notice requirement was found. Private commercial work needs no preliminary notice. Before filing a lien, a claimant without a direct contract with the owner must give the owner written notice of the claim (Ala. Code 35-11-210). This is a notice before the lien, not a preliminary notice. Check this point in the statute.

Sources

Confidence: medium. This is a reference to check, not legal advice. Check the statute named on each point before you rely on it. As of 2026-11-19.