BuildProofFree tool

Pay App Checker

Upload a pay application — the G702 summary, the G703 continuation sheet, or both — and see what does not add up before it goes out. No account, no email.

What it checks

On the G702: line 1 plus line 2 equals line 3; 5a plus 5b equals 5; line 4 less line 5 equals line 6; line 6 less line 7 equals line 8; line 3 less line 6 equals line 9. Whether the application number, the period, the contractor’s signature and the notary block are shown.

On the G703, line by line: D + E + F equals G; G ÷ C matches the percent printed; H equals C less G; the retainage in column I is one rate across the lines. Any line billed past its scheduled value (stored material counts toward the line). Each column adds up to its total, and the totals match the G702 (C to line 3, G to line 4, I to line 5).

Retainage: line 5a against its percent of completed work, 5b against its percent of stored material, and line 7 against what was billed before this period.

How the figures are read

A reader copies each figure exactly as it is printed; every sum and difference is then worked out by code, in cents. A figure the document does not show is marked not checked — never guessed and never counted as a pass. If the file cannot be read, the page says so and nothing is reported as fine.

A finding names a gap on the document and quotes the printed figures behind it. It does not judge the work, and a flagged line can be right (an agreed different retainage rate, for example) — it is named so it can be confirmed.